Artemis III SLS Core Stage Stacked and Joined to Solid Rocket Boosters inside VAB at NASA Kennedy

NASA’s Artemis III SLS (Space Launch System) core stage is integrated alongside the twin solid rocket boosters on Oct. 28, 2026 inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida. Credit: NASA

KENNEDY SPACE CENTER/TITUSVILLE, FL – Fantastic news! In a show of continuing rapid progress – the giant SLS Core Stage is now officially stacked for NASA Artemis III earth orbiting astronaut mission scheduled in 2027 – targeted to test rendezvous and docking procedures to prototype commercial human lunar landers from both Blue Origin & SpaceX, NASA announced today, Oct. 28, via a press release with several images.

Technicians working inside of the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida carried out the complex task today, Oct. 28 – lifted the 212-foot rocket stage.

As NASA had announced last week at the ‘Artemis Acceleration” news briefing for the media.

NASA’s Artemis III SLS (Space Launch System) core stage is integrated alongside the twin solid rocket boosters on Oct. 28, 2026 inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida. Credit: NASA

“The core stage of the Artemis III rocket is officially stacked,” NASA confirmed Oct 28.

“To integrate the core stage, employees use a one-of-a-kind lifting beam to lift it inside of the Vehicle Assembly Building at NASA’s Kennedy Space Center. Then, the core stage is joined with the completed solid rocket booster motor segments.”

NASA’s Artemis III SLS (Space Launch System) core stage is integrated alongside the twin solid rocket boosters on Oct. 28, 2026 inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida. Credit: NASA

They lifted the 21 story core stage with the lifting beam and placed it between the twin SRBs and onto the mobile launcher

Engineers with NASA’s Exploration Ground Systems completed integrating the aerodynamic nose cones onto the left and right forward assemblies on the twin SLS (Space Launch System) solid rocket boosters, finishing their stacking operations for Artemis III inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida on Wednesday, Sept. 30, 2026. Each forward assembly contains an aerodynamic top, a forward skirt housing avionics, and frustum housing motors that allow the boosters to separate from the SLS core stage after launch. Credit: Jean Wright/SpaceUpClose.com

“The core stage of the Space Launch System rocket serves as the backbone of the rocket, supporting the weight of the payload, upper stage, and Orion spacecraft, as well as the thrust of its four RS-25 engines and two five-segment solid rocket boosters attached to the engine and intertank sections.”

After completing testing and checkouts teams will roll the core stage and booster so called ‘short stack’ out to Launch Pad 39B.

Artemis III core stage during media tour in Oct 2026 inside the Vehicle Assembly Building’s High Bay 2 at NASA’s Kennedy Space Center in Florida. Will be transferred to High Bay 3 for attachment to twin SRBs. Credit: Jean Wright/SpaceUpClose.com

Then they will conduct a tanking test where over 730,000 gallons of cryogenic liquid hydrogen and liquid oxygen fuel will be loaded only into the core stage and launch teams will practice countdown procedures and timelines – as well as check for any gaseous leaks.

The Artemis III mission will last about 14 to 17 days and the foure person multinational astronaut crew will test rendezvous and docking between their Orion spacecraft and the two dissimilar commercial lunar landers

Engineers with NASA’s Exploration Ground Systems completed integrating the aerodynamic nose cones onto the left and right forward assemblies on the twin SLS (Space Launch System) solid rocket boosters, finishing their stacking operations for Artemis III inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida on Wednesday, Sept. 30, 2026. Each forward assembly contains an aerodynamic top, a forward skirt housing avionics, and frustum housing motors that allow the boosters to separate from the SLS core stage after launch. Credit: Jean Wright/SpaceUpClose.com

The purpose of Artemis III is carrying put critical preparation that will lead to future Moon landings as part of NASA’s Artemis return to the Moon with astronauts landing at the lunar South Pole.

The Artemis III mission comprises crewmembers NASA astronauts Randy Bresnik, Frank Rubio, Andre Douglas, and ESA (European Space Agency) astronaut Luca

NASA had already completed stacking of the twin Solid Rocket Boosters (SRBs) motor segments destined for use on NASA’s Artemis III mission launching to low Earth orbit targeting NET later summer 2027 from NASA’s Kennedy Space Center in Florida.

Media including Jean Wright of Space UpClose were taken on a tour inside the NASA’s Vehicle Assembly Building (VAB) in early October to capture the progress of the Artemis III five segment SRB assembly and stacking operations atop the mobile launcher inside the VAB High Bay 3 at NASA KSC

The SRB stacking work by engineers with NASA’s Exploration Ground Systems was completed on Sept. 30

Concurrently, teams also completed installation of all four RS-25 engines on the SLS core stage.”

Enjoy our SRB stacking photos and core stage photos taken by Jean Wright for Space UpClose  here.

 

The Artemis III SLS core stage was transported inside NASA’s Pegasus barge from NASA Michoud and arrived at the KSC Complex 39 Turn Basin Wharf at KSC Press Site on April 27th, to NASA’s Kennedy Space Center.

Enjoy our core stage arrival, offloading and Pegasus tour photos taken by Ken Kremer and Jean Wright for Space UpClose

NASA’s top four-fifths of the SLS (Space Launch System) core stage for the Artemis III mission is offloaded from the agency’s Pegasus barge on Tuesday, April 28, 2026, after arriving at the Kennedy Space Center in Florida the prior day. Artemis III will launch astronauts to Earth’s orbit aboard the Orion spacecraft on top of SLS to test rendezvous and docking capabilities between Orion and commercial spacecraft from SpaceX and or Blue Origin needed to land Artemis IV astronauts on the Moon in 2028.
Credit: Ken Kremer / Spaceupclose.com

The Artemis III core stage was then moved and placed horizontally in the transfer aisle of the VAB before being lifted into High Bay 2, where it was connected to the engine section and its boat-tail, which were integrated in August 2025.

NASA’s SLS core stage for the Artemis III mission is offloaded from the agency’s Pegasus barge April 28, 2026, and moved to the VAB for processing and stacking at the Kennedy Space Center in Florida. Credit: Ken Kremer / Spaceupclose.com

At 212 feet tall when fully assembled, the core stage houses two propellant tanks that collectively hold more than 733,000 gallons of super-chilled liquid propellant to fuel four RS-25 engines, as well as the flight computers, or avionics, that act as the brains of the rocket to control flight during ascent.

NASA’s Artemis II Space Launch System (SLS) rocket and Orion spacecraft atop mobile launcher at Launch Complex 39B at NASA’s Kennedy Space Center in Florida. NASA’s Artemis II test flight will take 4 astronauts around the Moon and back to Earth with launch opportunities beginning April 1, 2026. Credit: Ken Kremer/SpaceUpClose.com

This marks the first time core stage assembly operations were taking place at NASA Kennedy.

NASA’s Artemis II SLS rocket and Orion spacecraft, secured to the mobile launcher, inside the Vehicle Assembly Building began rollout to Launch Complex 39B at NASA’s Kennedy Space Center in Florida at 12;20 a.m. March 20, 2026. View from remote camera on level 16 in High Bay 4 inside the VAB set by Ken Kremer. Credit: Ken Kremer/SpaceUpClose.com

The Artemis I & II core stages were fully assembled at Michoud before shipping to KSC

Jean Wright of Space UpClose poses with Artemis III core stage during media tour in Oct 2026 inside the Vehicle Assembly Building’s High Bay at NASA’s Kennedy Space Center in Florida. Credit: Jean Wright/SpaceUpClose.com
Jean Wright of Space UpClose poses with Artemis III SRB stack during media tour in Oct 2026 inside the Vehicle Assembly Building’s High Bay 3 at NASA’s Kennedy Space Center in Florida. Credit: Jean Wright/SpaceUpClose.com
Ken Kremer of Space UpClose reporting on NASA’s Artemis III core stage arrival and transport into the VAB on April 28, 2026 at the Kennedy Space Center, FL. Credit: Ken Kremer / Spaceupclose.com

x

 

Ken Kremer

Watch for Ken’s continuing onsite coverage of NASA, SpaceX, ULA, Boeing, Lockheed Martin, Northrop Grumman and more space and mission reports direct from Kennedy Space Center and Cape Canaveral Air Force Station in Florida and Wallops Flight Facility in Virginia. Stay tuned here for Ken's continuing Earth and Planetary science and human spaceflight news. Dr. Kremer is a research scientist and journalist based in the KSC area, active in outreach and interviewed regularly on TV and radio about space topics. Ken’s photos are for sale and he is available for lectures and outreach events.

One thought on “Artemis III SLS Core Stage Stacked and Joined to Solid Rocket Boosters inside VAB at NASA Kennedy”

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.